Teknologi Tenaga Perlis Consortium Sdn Bhd (TTPC) was incorporated on 11th July 1996 and was granted a license by the Minister of Energy, Telecommunications and Posts to build, own and operate a power plant in Malaysia.
TTPC is one of the six Independent Power Producers (IPPs) established under the Malaysian Privatisation Scheme to supply electricity to the national electric utility company, Tenaga Nasional Berhad (TNB).
Our 650MW combined cycle power plant in Perlis achieved Commercial Operation Date on 31st March 2003, completed in a record time of 21 months from financial close with no cost overrun.
TTPC was incorporated on 11th July 1996.
Granted license by the Minister of Energy, Telecommunications and Posts to build, own and operate a power plant.
Global E-Technic Sdn Bhd (GET), a wholly owned subsidiary, was incorporated on 27th April 2001 for O&M services.
Achieved Commercial Operation Date (COD) on 31st March 2003.
Received Bronze Engineering Award and triple ISO certifications.
Bonds upgraded to AA1 rating by RAM Rating Services.
A wholly owned subsidiary of TTPC, incorporated on 27th April 2001 with the primary objective of performing operation and maintenance services on TTPC's power plant.
Total TTPC Perlis Power Plant Project cost